clearing and grubbing
1.Scope:
This work will shall consist of cutting, removing and
disposing of all materials. Such as trees, stumps, roots, grass, top organic
soil not exceeding 150mm in thickness etc. it includes necessary excavation,
backfilling of pits resulting from uprooting of trees and stumps to required
compaction, handling. Salvaging and disposal of cleared material. Clearing and
grubbing shall be performed in advance of
earth work operation, and accordance with the requirements of MORTH
specification.
2. Methods,
Tools and Equipment:
a) If the area has thick vegetation/roots/trees, a
crawler or pneumatic tyred dozer of adequate capacity may be used for clearance
purposes. The dozer shall have ripper attachments for removal of tree stumps
etc. as per MORTH
b) Within excavation
and fill lines shall be cut to such depth below ground level that in to
case these fall within 500 mm of the sub grade.
c) On area beyond these limits, trees and stumps required
to be removed as directed by the
d) All branches of trees extending above the roadway
shall be trimmed as instruction of the competent authority.
e) All excavation below the general ground level arising
out of the removal of trees, stumps, etc. shall be filled with suitable material
and compacted comprehensively so as to make the surface at these parts conform
to the surrounding area.
f) Ant-hills both above and below the ground, as are liable to collapse and obstruct free sub soil water flow shall be removed and workings, which may extend to several meters, shall be suitable treated.
3. Disposal
of Material:
1) All Material arising from clearing
and grubbing operations shall be the property of government and shall be
deposited as instruction of the competent authority.
2) Staking of stumps, boulders, stones
etc. shall be done at specified location with all lifts and up to a lead of
1000 m.
3) Unwanted material afterbdozing shall be disposed.
4. Safety Measures:
· Care
shall be taken while cutting the trees
· The
cutting material shall not disturb the live traffic
·
The cutting crew shall
wear PPE·s, reflective jackets
· The
cutting area shall be protected with safety boards and cones
· Take
care of near by passing electrical lines and utilities.
·
Flagmen shall be provided
on both side of cutting area to regulate live traffic.
S.No. |
Description
|
YES |
NO |
NA |
1 |
Removal and disposed of trees,
shrubs, bushes, stumps, roots, grass, weeds, top organic soil and other
rubbish |
|
|
|
2 |
Required excavation carried out |
|
|
|
3 |
Backfill the excavated pits with
suitable material |
|
|
|
4 |
Compacted the backfill material
properly |
|
|
|