10.4
Identification of Non-conforming Report and
Management
10.4.1 Non –
Conformance Report Notification (NCRN)
EPC shall
implement a system to identify and provide a disposition for all
non-conformances associated with the works. The authorized representative of
EPC shall be responsible for recording of non-conformances by issuing a
Non-Conformance Report Notification (NCRN) to Subcontractor. All NCRN shall be
forwarded to the Project Manager / Chief Project Manager for the determination
of a disposition with concurrence by the Project Manager of EPC / Sub
contractor.
Non-conformances
identified during inspection, testing and verification activities shall be
addressed at the workforce by issue of a Inspection note by the respective
section to the Project Manager. Based on that NCRN (See Proforma in Appendix
A1) shall be issued.
All NCRN shall
be reviewed by the Project manager / Chief Project Manager and assigned a
disposition as follows, either repair, rework, use-as-it-is.
All
NCRN shall be submitted to the Sub Contractor for their concurrence.
The Nonconformance
Report shall detail the following:
1.
A
unique identification number based on inspection report.
2.
Reference
to the drawings/ specification.
3.
Location
within the Works.
4.
Description
of the non-conformance.
5.
Authorized
representative signature and date.
6.
Chief
Project Manager’s approval of action with respect to disposition.
7.
Re-inspection
acceptance signature and date by the authorized representative or his
representative.
8.
EPC
authorized person’s approval/disapproval.
The AGM(QA/QC)
/QME shall maintain a Nonconformance Report Register to monitor the sign of the
assigned disposition(See Proforma in
Appendix A4). The Register shall be reviewed on a monthly basis and a report
provided to the Chief Project Manager / Project Manager.
10.4.2
Corrective Action Request
EPC shall promptly implement corrective action
to address conditions identified as adverse to quality ensuring that the
actions are effective and that their effectiveness continues. The Project
Manager (with consultation from all responsible parties) shall be responsible
for approval of the proposed corrective action. The AGM (Highway) / AGM(
Structure) / AGM (QA/QC) shall be responsible for identifying the need for,
proposing and assessing the effectiveness of corrective action. Where
conditions adverse to quality, are identified, the concerned Engineer shall
complete the proposed Corrective Action Report. The Project Manager shall
approve the proposed Corrective Action. The concerned section in-charge shall
monitor the implementation and effectiveness of the Corrective Action.
Outline of Activities
The
AGM (QA/QC) shall monitor implementation of Corrective Action using the
Corrective Action Report Register (Proforma in Appendix A4). The Register shall
be reviewed on a fortnightly / monthly basis and a report provided to the Chief
Project Manager.
The
AGM (QA/QC)/QME shall also implement a corrective action request register for
CARs issued by the concessionaire and a register of nonconforming report /
service notification – correction action requests.