INSTALLATION OF BORED
CAST IN SITU PILES (DMC Method)
1. Site clearance Layout and Survey Work
The site shall be cleared of existing
structures, trees, bushes, heap of earth etc. at the approximate location of
pile groups on various bridges.
(1.1) The center line pillars and benchmark shall be
established at the site of each bridge with the help of already available
reference points and benchmarks. The center line pillars shall be masonry
pillars of sufficient depth in order to have permanent reference during the
entire construction of the bridge and of sufficient height so that height of
pillar plus height of instrument can mark the center line right up to top of
the superstructure. These center line pillars shall be duly checked &
approved by the Engineer, before taking up any permanent works.
(1.2) With the help of above center line
pillars center line of each pile group longitudinally as well as transversely
shall be established.
(1.3) Based on above pile group layout a
location of initial load test pile shall be selected in such a manner that if
fairly represents the entire piling work on a particular bridge and area is
reasonably leveled to create a platform to carry out the initial load test.
This location shall be marked vis-Ã -vis the center line of the bridge and got
approved from the consultant before taking up actual execution of the initial
test pile.
(1.4) The setting out of various piles in a
particular group shall be carried out with respect to the center of group and
shape of the pile cap shall be marked. After setting out of each group Surveyor
shall take spot levels (site levels) of existing ground before taking up
excavation work for creating a working platform for installation of working
piles. These spot levels shall be checked and jointly recorded with the
consultant.
2. Earth Work / Excavation for working
platform for installation of bored cast in situ piles.
Depending on depth of excavation for pile cap
and unstable sub-soil conditions, suitable depth shall be excavated for each
pile group in order to create a working platform for erection of piling
equipment and installation / routine load testing of piles. Suitable shoring if
required, shall be provided on the sides to avoid any collapse of sides.
However, if such protection is required a sketch of the same shall be prepared
and got approved from the Engineer before taking up the excavation as a safety
requirement.
3. Installation of bored cast in situ piles.
(3.1) General.
It is proposed to carry out the boring of cast
in situ piles with the help of a heavy duty tripod hoisting a DMC (Direct Mud
Circulation) cutting tool as per the propriety design of the piling agency and
operated with the help of diesel / electrically operated power winch.
In the DMC method of piling, the initial
boring up to a depth of 1.5 m is done using the boring tools and guiding
casing. The bore is then filled with drilling slurry and further boring up to
the founding level is carried out by continuous slurry circulation with DMC
boring tools. The purpose of a boring slurry is mainly to muck out the
excavated material from the bottom of the bore to a settling tank on ground. In
the DMC method the muck is carried out to the surface through boring slurry and
is deposited in the settling tank through slurry coming out of the bore. The
slurry is continuously circulated under the required pressure through DMC
tubes. After the bore is completed up to the required depth, fresh slurry shall
be pumped through DMC tool / tubes while DMC is resting at the bottom of the
bore till such time that all the muck / loose materials are removed from the
bore. Various steps of boring of piles shall be as follows:
(3.2) Installation of Temporary casing.
After setting out of the pile location by
surveyor, a temporary casing shall be installed prior to the excavation to
support the upper layer of weak soil. The length of the temporary casing shall
be decided during installation of the initial test pile and generally be the
same at least in a particular group. Casing installation shall be carried out
with the help of a hammer attached to the tripod and winch. The control of
verticality of piles within the allowable tolerances as prescribed by the
Technical Specification, shall be performed during the installation of the
temporary casing.
(3.3) Boring Process:
After installation of temporary casing and
checking of its location and verticality the boring DMC method shall be
started. The drilling slurry consists basically of water and DMC powder in
colloidal state. The drilling slurry will be prepared by mixing clean water
with the appropriate DMC powder, to make a slurry which shall serve the purpose
of a carrier for the excavated muck for the entire period of boring, during
placement of concrete up to completion of the pile construction. High
turbulence mixers shall prepare the slurry and, before it is used, it shall be
left to season in a storage tank for at least 24 hours. Tests to determine
density, viscosity and pH value shall be applied to the colloidal suspension
pumped through DMC reds to the bore. The fresh slurry shall have the following
properties. :
- Density g/ml < 1.05 g/cc
- Marsh Cone Viscosity 30-40 seconds
During the boring operation the drilling tool
is lowered into the bore with percussion movement. Slurry of required specific
gravity shall be pumped through the DMC rod by a vertical pump installed on the
slurry tank. Simultaneously the DMC rod shall be moved up and down by winch.
The slurry coming out from the bottom of the bore, shall be collected through a
gravity flow channel in the slurry tank. During the flow in the channel the
muck will settle and only slurry shall get collected in the tank.
Boring will be continued till the founding level
is reached. If rock is encountered up to a maximum strength of 400 kg/cm2 a
special rock chisel shall be used.
(3.4) Pile Base Cleaning:
Before placing concrete, measures shall be
taken to ensure that there is no accumulation of sediments at the base of the
bore. A sample of the slurry suspension shall be taken from the base of the
bore using a sampling device and checked for its density and viscosity as per
the specifications.
(3.5) Installation of Reinforcement Steel
Cage:
The steel cage, pre-assembled in as many
sections as needed and complete with the appropriate spacers and stiffeners
will be lowered into the hole by the tripod. The quantity, type and size of
steel will be according to the Good for construction drawings and
specifications.
(3.6) Installation of the Tremie Pipe:
Prior to concrete pouring operation, a 250 mm
internal diameter pipe of full length, assembled together from sections of 1.20
– 1.50 meter each, shall be lowered down to the bottom of the pipe and then
lifted up by 200 to 300 mm. The top of the Tremie pipe shall be fitted with a
feeding hopper to receive concrete either directly from a transit mixer or
concrete pump. It shall be ensured that all the joints between the Tremie
segments and between the funnel and Tremie are watertight.
(3.7) Concreting:
Concreting in pile under water shall be done
with the use of the Tremie method to permit deposition of concrete in
successive layers without permitting the mixing of water / slurry with the
concrete.
Ready mixed concrete with a slump of about 150
mm to 180 mm, produced from the mixing plant with weigh batching shall be used
to ensure a smooth flow of concrete in the Tremie pipe.
The toe of the Tremie pipe should always
remain immersed at least 2m in concrete, during entire casting to prevent
intrusion of drilling slurry / water as the case may be.
As the pouring operation continues, the rise
of concrete level inside the bore shall be monitored and recorded. As the level
of concrete rises inside the bore, the Tremie pipe shall also be raised by
removing 1-2 sections of Tremie pipe. While raising the Tremie pipe it shall be
ensured that the Tremie pipe always remains immersed @ 2m inside the concrete.
Pouring of concrete shall continue until the designed level of pile is achieved
and sufficiently above thereafter to allow for subsequent cutting of pile to
get sound concrete at cut-off level. Depending upon the length of casing the
temporary liner shall be extracted, if required
0 Comments
Please do not enter any spam link in the comment box.