SOIL – CEMENT STABILISATION IN ROAD CONSTRUCTION.
1. DESCRIPTION OF ITEM :
Construction of top 150mm of subgrade and earthen
shoulders with 2% (two percent) cement by weight mixed with approved soil
including all leads and lifts as per Technical Specifications modified Clause
305.7.
Mix in place method will be adopted. In this method the mixing of the soil – cement is done at the place where it will be finally placed. It consists of the following steps:
a) The
Sub grade is cleared of all undesirable materials such as boulders, debris,
stumps etc. It is then leveled to the required formation level and true to the
camber.
b)
The leveled sub grade is scarified to a depth equal
to the proposed thickness of the soil cement mix i.e 150 mm. This will be done
by disc harrows pulled by the tractors.
c)
The scarified soil is then pulverized till all the
particles pass through 26.5 mm sieve and 80% pass through 5.6mm sieve. (Refer
table 400.5 MOST Specification). This will be achieved by using disc harrows
pulled by tractors.
d) The pulverized soil is properly shaped to require grade and cement is spread uniformly over surface. The cement to be used is of grade 43 and the quantity to be used is 2% by weight & is of dry density of soil. It is then intimately dry mixed till the mixture gets uniformly mixed.
e) The required quantity of water is sprinkled over the surface and the wet mixing is done till the mixture is uniform in the colour. However the mixing should not be continued after the cement has started hydrating, as it would result in a loss of strength. The moisture content compaction is checked vide IS 2720 (Part 2) shall neither be less than the OMC corresponding to IS 2720 (Part 8) not more than 2% above it.
The operation (d) & (e) should be completed within 3 hours of spreading the cement.
f) The surface is properly graded using the grader.
g) Compaction immediately after the grading of the mixed material, compaction will be carried out with smooth drum vibratory rollers. Rolling shall commence at the edges and progress towards the center except at super elevated portions where it shall commence at the inner edge and progress towards outer edge. During rolling the surface shall be frequently checked for grades and cross fall any irregularity corrected by loosening the material and removing / adding fresh material. Compaction is to continue until the density achieved is at least 98% of the maximum dry density for the material determined is accordance with IS 2720 (Part 8 )
Care is to be taken to see that the compaction of the mix is completed within two hours of its mixing.
h) The compacted soil- cement is most cured for 7 days by
keeping it damp water will be sprinkled every four hours for the first 3 days
and every 8 hours for the balance four days.
3. CONSTRUCTION EQUIPMENT:
A stretch of 50 m will be taken for operation. The following equipment shall be used:
a) Disc Harrows with tractor for scarifying pulverizing Mixing
b) Motor Grader for leveling
c) Vibratory Compactor for compaction
d) Water tanker with sprinkler for mixing of water curing.
4. THE
FOLLOWING QUALITY CONTROL TESTS ARE PROPOSED:
b) Cement
content Test certificate with
consignment.
Regularly
through procedural check.
c) Degree
of pulverization Each stretch by sieving three different
samples
d) Moisture
content One test for each stretch (approx 250 sqm)
e) Density
of compacted layer Each stretch
f) CBR
test on a set of 3 specimen Drawn from 1
Km each
g) Deleterious
Material Already tested for
the soil for the sub-grade
h) Surface finish {As per MOST Specification Clause 902}
5. TRAFFIC ARRANGEMENT:
No traffic of any kind will ply over completed Sub
base except the water truck used for sprinkling of water
0 Comments
Please do not enter any spam link in the comment box.