BOX CULVERTS
This item of work deals with
construction of Box culverts with approved materials as per the terms of
contract agreement.
1. General
The construction shall confirm to the
specific alignment, lines and grades given in the drawing.
The materials used shall adhere
to the section 1000 of technical specifications. The concrete used shall be of
approved design mix and shall confirm to section 1700 of technical
specifications.
2.
Procedure
Diversion
of Water:
The requisite and efficient methods are adapted to suit the particular
need of diverting the water.
Excavation:
- Layout marking will be done as per
approved working drawing and ground levels will be taken and recorded
jointly
- Excavation will be done conforming to
the lines, grades, slopes and levels as shown on the approved working
drawings, as per the specification clause 304.3.2
- If required dewatering will be done as
per the specification clause 304.3.3
- All the excavated materials will be
disposed such that the working space will not effect, as per the
specification clause 301.3.11
- Excavation in Hard Rock will be done as
per specification clause 301.3.5
- Preparation of foundation will be done
as per specification clause 301.3.4
- if there is any slips & slip outs
in the excavation will be removed
- Filling below foundations up to require
level and backfilling will be done with approved material in layers not
exceeding 150mm compacted thickness. The compaction will be done with the
help of suitable equipment such as mechanical tamper, plate vibrator etc.
after necessary watering as per specification clause 301.3.7
Concreting:
Base
Slab: The
reinforcement shall be placed in position and shuttering is erected to exact
dimensions of base slab and after due checks, base slab is concreted to the top
of bottom haunch and joints is maintained as detailed in drawing.
Walls: The walls are cast to bottom
level of upper haunch. The procedure adopted will be same as base slab.
Top
slab: The shuttering is made to support the top slab and necessary care is
taken to seal the joints to avoid
slurry loss from concrete through joints.
The steel is positioned and concreted.
The
formwork is removed after due time as per norms and blemishes, if found, are
made good.
The inlet
& Outlet structures, the aprons and floor protection works are constructed
in similar progression.
The
surroundings are cleared of all surplus stocks, waste materials etc., and
cleaned. The structure is finished as per specifications including necessary
markings, paints etc., and completed.
3. Equipment/Machinery:
1.
Poclain/
JCB
2.
Auto
level with accessories
3.
Transit
Mixers
4.
Needle
Vibrators
5.
Cube
Moulds