EARTHWORK IN EXCAVATION ,FILLING AND SUBGRADE IN ROAD WORKS.

    Earthwork in excavation,Filling and subgrade

  Earthwork in excavation

The work of excavation would commence as soon as the area under construction has been cleared by survey team. The excavated material will be transported directly to either of the followings

n  If the soil is suitable for embankment works - would go to embankment site. Internally transportation distance will be reached approximately 10km.

n  If the soil is suitable for re-handling works of embankment – would be stocked permitted area then re-handled to site.

n  If the soil is not suitable – would be dumped in the earmarked area. Site investigation will be reported for the approval of disposal area which is located within 10 Km.

n  Required number of tipper for transportation will be provided as mentioned in construction programme.

The areas where excavated soil is to be used would be laid to fine lines and levels then will be watered and compacted as per specifications. To handle the required  quantity of earthwork substantial number of excavators, front-end loaders, dozers and soil compactors would be deployed as mentioned in construction programme.

Quality control for Earth work in Excavation

n  Excavation for structures shall consist of the removed of material for construction of foundation for bridges, culverts, retaining walls, pipe culverts etc.. So in accordance with the requirements of these specifications, we will carry out excavation to the full depth of required founding level. Even we shall carry out the excavation whether a line of vetical to 2 horizontal in stressed zone from an adjouring structure.

n  Where cofferdams are required, these shall be carried out to adequate depths and heights which will be safety designed and constructed to make watertight.

n  Sufficient clearance for inspection shall be ensured for construction activities inside the enclosed area.

n  Pumping from the interior of any foundation enclosure will be done in such a manner as to preclude the possibility of the movement of water through any fresh concrete.

n  Contractor  take all precautions in diverting channel and its discharging the drained water as not to cause damage to the works or any other property and material.

 

   Earthwork in Filling and subgrade

These method statement can be apply to the construction of embankment, earthen shoulder and subgrade


Material

The material used in embankments shall be soil, moorum, gravel or a mixture of these or ant other material approved by Engineer, and be free of logs, stumps, roots, rubbishs and any other ingradient likely to deteriorated affect the stability of the embankment.

And the size of the coarse material shall ordinary not exceed 75mm and the maximum particular size shall not be more than two-thirds of the compacted layer for the embankment

 Contractor will list the material of borrowpit in the quality control laboratory for the identification of right material and with use the same on approval of Engineer-in-charge.

Operations

Seting out

n  The limits of embankment will be marked by fixing batter pegs on both side at regular intervals as guides before commencing.

Dewatering

n  If any stagnant water for the excavation and embankment specially near by  river or any other place, it will be removed by pumping or bailing and the area of embankment foundation keep dry.

n  1” ~ 4” engine type dewatering pump will be provided as need.

Spreading

n  The embakment material will be spread and finished in layer of uniform thickness not exceeding 200mm compacted thickness over the entire width of embankment by dozer and motor grader, and required quantity of equipment is mentioned in construction programme.

n  Moisture content of the material will be checked at the site of placement prior to commencement to compaction, and if found where water is required to be add, water will be sprinkled uniformly using water tanker without any flooding, and mixed in soil by blading, discing or harrowing until uniform moisture content is obtained the depth of the layer.

Compaction

n  The compaction will be done with the help of vibratory roller capacity 8~10 ton static weight with plain or pad foot drum or heavy pneumatic tyred roller of adequate capacity of achieving required compaction.

n  Contractor will demonstrate the efficacy of the equipment, intends to use by carrying out compaction trials and the procedure to be adopted for these site trials will be submitted to the Engineer for approval.

n  Each layer of the material will be thoroughly compacted to the densities specified in the MOST specification as following;

l  Relative compaction of Embankment shall be not less than 95% of MLDD (Maximum Laboratory Dry Density)

l  Relative compaction of Subgrade and Earthen shoulder shall be not less than 97% of MLDD