Prestressing work for Bridges
1) Reinforcement work
n Before placing concrete,
reinforcement is fabricated sufficiently and correctly as required
n Reinforcement shall be tied
with accurate type, diameter, length, distance and placed position. The ties
and spacer shall be firm as required.
2) Spiral duct(sheathe) installation
n The spiral duct is connected
to reinforcement of slab.
n The spiral duct should be
installed at correct position horizontally and vertically as specified.
n The spiral ducts are joined
to each other by connection pipes of 200mm long.
n The connecting points are
surrounded 3 times by PVC cohesive tape to prevent cement and water from coming
into ducts.
3) Installation of anchor base
n Anchor base is joined by
bolt M12
n The anchor shall be
installed at the center of the spiral duct
n The connecting points between
anchor head and spiral duct are surrounded 3 times by PVC large-sized cohesive
tape.
4) Form installation
n The formwork of slab shall
be done correctly as designed
n The slits on the form shall
be filled by rubber gasket or soft pieces as waterproof element.
n Forms shall be located and
connected carefully by bolts as designed.
5) Concrete mixing
n Concrete materials such as
cement, sand, aggregate etc. shall be the same quality as approved by the
Engineer.
n The slab shall be mixed with
the approved admixture
n The materials measurement is
taken by automatic electronic scale system.
6) Placing concrete
n The concrete will be placed
by concrete pump and crane with bucket capacity of 0.5~1.0 m3.
n Concrete will be placed
layer by layer with the depth of 15-30 cm each, without interruption.
n The concrete is compacted by
the vibrators.
n The curing of slab concrete
is done during 7 days (3 shifts a day) after 10 hours from finishing. It is
watered 5 times in the daytime and 4 times in the nighttime.
7) Form demounting
n Side form of slab will be
removed after 3 days not less than 85% of the specified 28 day strength from
concreting
n It is not necessary to
remove bottom form. However, it shall be necessary to clear and coat with an
anti-cohesive substance after each time of casting and removing slab out of
casting base.
8) Prestressing work
(1) Equipment for construction
n Hydraulic oil pump: 4 nos.
n Hydraulic stressing jack
(2100 KN): 4 Nos.
n Grout mixer: 2 Nos.
n Grout pump: 4 Nos.
n Cable cutter: 6 Nos.
n Cable inserting machine: 2
Nos.
n Air compressor (9 m3/min): 2
Nos.
n High pressure water pump: 2
Nos.
(2) Inserting of cable
n When the strength of girder
concrete reaches 85% of the specified 28 day strength, the cable is inserted
into duct to carry out prestressing.
n The cable is inserted by
electric inserting machine with capacity of 7.5 KN, inserting speed of 24
m/min,
n Each strand is sealed at
ends to make it easy for inserting. The cable shall be slipping sufficiently.
n When projecting cable is
cut, 1m of cable shall be left at both side of cable to prestress later.
(3) Prestressing
n The tensile force of
stressing jack shall be at least 1.1 - .1.2 times stronger tan the tensile
force of cable.
n The stressing jack and oil
pump shall be tested before stressing.
n Each cable is stressed by 2
jacks at both ends of cable.
n Strestressing jack and
hydraulic oil pump shall be completely installed before stressing. Good care of
anchorage and cable position shall be taken to avoid twisting.
n Stress force of cable shall
be taken into consideration with inner lost of jack and anchor.
n The straining is divided
under loading steps in correspondence with value indicated on pressure gauge of
hydraulic oil pump. There are at least 5 steps.
n The first loading is about
10%. Design force is normally about 50 bar.
n The elongation of cable in
each loading step shall be recorded.
n There shall be an interval
of 4 – 5 minutes between loading steps to led cable relax.
n The stroke of jack shall be
reset under the principle of stress recover if it is shorter than the
elongation at one cable end.
n When pressure of jack
reaches its calculated design, put pump oil into jack. Automatic device of jack
is used to close the wedge with its pressure equal or less than 200 bar.
n After wedging, zero the
pressure of hydraulic jack and measure the cable retraction at 2 ends to get
the actual elongation.
n The elongation is the sum of
measure elongation at 2 ends excluding the cable reaction in the jack. The
elongation obtained shall meet the requirements of design. (That is calculated
under the actual elastic modulus of each cable.)
(4) Check and cut the cable
projection length.
n After getting inspection and
approval from the Engineer on prestressing the projecting cable length is cut.
n Electric plate sawing
machine with its function blade is used to cut the projecting cable.
n After cutting, the rest
length is about 25-30 mm far from the wedge.
(5) Grout pumping sequence
n The approval of grout shall
be given from the Engineer before pumping.
n The mix design of grout
shall be approved by the Engineer
n The strength of pumped grout
shall not be less than 20 Mpa.
n Grout is pumped into duct by
electric grout pump. The guiding pipe system is installed from the pump to the
duct of anchor head.
n The grouting is done
uninterruptedly. In case of stopping of pumping in 2 hours or more, grouting
shall be re-started after removing grout out of cable duct by water and air
compressor. The pumping pressure shall be maintained at 12-15 bar. When the
grout comes out at the other end of cable duct, adjust the pumping pressure
from 7 – 1.5 bar within 5 minutes. After that, lock valves at 2 ends and stop
pumping.
n All the pumping ducts shall
be sealed tightly on concrete surface and such sealing shall be removed after
12 hours from finishing pumping.
CHECK LIST FOR PRESTRESSING WORKS
S.No.
|
Description |
OK |
NOT OK |
NA |
1 |
Tendon
profile (Vertical) |
|
|
|
2 |
Tendon
profile (Horizontal) |
|
|
|
3 |
Fixing
of Anchorages as per drawing |
|
|
|
4 |
Fixing
of bursting reinforcement |
|
|
|
5 |
Cut
length of strands |
|
|
|
6 |
Gripping
length |
|
|
|
7 |
No
of strands per tendon |
|
|
|
8 |
Grout
vent |
|
|
|