CONSTRUCTION OF WELL FOUNDATIONS.
A) SETTING OUT:
The
centerline of the road will be marked, in the portion where the bridge is to be
constructed, based on the GPS points already available. Subsequently, the
center of the individual wells will be marked. A temporary benchmark will be
established near the well foundations and got approved by the Engineer.
B)
GENERAL
DESCRIPTION:
Ø LOCATION OF BRIDGES HAVING WELL FOUNDATION :
Sl. |
Bridge No. |
Chainage
|
No. of Well
|
Dia of Well
|
|
|
|
|
|
D) MACHINARY TO
BE USED:
Crane
Grab
buckets – capacity 1.5 cum
Excavator / J.C.B. which
ever is applicable
Chisels
of appropriate sizes
Batching Plant of capacity 30 M3/ hr
Weigh
Batches of Capacity 500 Kg.
Petrol/Electrical
Vibrator & 60mm Nozzle.
De-Watering
Pump
Transit
Mixer
Other
relevant tools.
E) SEQUENCE FOR
CONSTRUCTION OF WELL FOUNDATION:
01. CUTTING
EDGE :
Ø
The mild steel cutting edge will be
fabricated in four segments.
Ø
It will place and assembled in site at
the time of executing well foundations.
Ø
The cutting edge will be erected on
firm level ground.
Ø After assembling of cutting edge, steel strakes of required height as per drawing will be welded.
Ø
Cutting edge will be prepared as per
MOST Clouse No. 1900.
02. WELL
CURB :
Reinforcement work
Ø
Steel reinforcements will be assembled
as per drawing.
Ø
The bottom ends of vertical rods will
be fixed securely to the cutting edge by welds.
Ø
Epoxy Coated Steel only will be used in
the reinforced concrete.
Ø
Bar Bending Schedule will be prepared
according to the drawing and submitted for Engineer's approval.
Ø
The coated reinforcement bars should be
protected against any damage
Ø
The reinforcement bar should be tied
together properly at every intersection and lapping.
Ø
Reinforcement Steel will be as per MOST
Clouse No. 1600.
Ø
The design drawing for formwork will be
submitted for approval to the Engineer.
Ø
Formwork will be as per MOST Clouse No.
1500.
Concreting Work
Ø
Concreting will be done in one
continuous operation.
Ø The concreting layers will be limited to about 450mm.
Ø Adequate No. of Needle vibrator will be used for proper compaction of concrete.
03. WELL
STEINING:
Ø
The height of steining shall be
calibrated by making four gauges.
Ø
The gauges will be start with zero at
bottom of the cutting edge.
Ø
Marking of the gauges will be done
carefully with a steel tape.
Ø
Details’ drawing for shuttering and
supporting arrangement is as per approved Drawing.
Ø
Steel formwork of a height of 1.8m will
be provided for the well steining.
Ø The formwork on outer face of well steining will be removed after 24 hours of concreting & inner face will be removed within 48 hours.
Reinforcement work
Ø
Steel reinforcements will be assembled
as per drawing.
Ø
Wherever necessary, reinforcement will
be fixed by welding process.
Concreting Work
Ø
Concrete cover block of required size
will be provided for reinforcement work.
Ø
Regarding concrete procedures please
follow sequence 3.
Ø Laitance formed top surface of lift shall be removed to expose coarse aggregates before setting of concrete for the next lift.
05. WELL SINKING:
Ø
The well will be sunk by excavating
material uniformly from inside the dredge hole.
Ø
The well will be uniformly seated at
the founding strata. Water jetting may be employed for well sinking wherever
necessary.
Ø Loading of the well with knetledge will be placed in an orderly on the loading platform. Loading will be commenced only after 48 hours of concreting.
Ø
Tilts and shifts will be carefully
checked and recorded in the format. Wherever any
tilts is noticed adequate preventive measures like placing eccentric knetledge,
pulling, strutting, anchoring or dredging unevenly, water jetting etc. shall be
adopted before any further sinking.
Ø After a portion of well has been sunk, another height of well steining will be cast and further sinking will be carried out.
Ø
Well sinking
tilt shift format has to recorded jointly with Engineer.
Ø
Before commencing plugging, all loose
material from the bottom of the well will be removed.
Ø
For bottom plug, concreting will be
done by tremie pipe method.
Ø Concrete mix will be as per drawing. Concreting work will be done in one continuous operation till the concrete filled up to the required height..
07. SAND FILLING:
Ø
Sand filling will be started after a
period of 3 days of laying of bottom plug.
Ø
Sand will be filled up to the bottom of
top plug, as mentioned in drawing.
Ø Sand will be cleaned and free from earth, clay, clods, roots, boulders etc. Compaction will be done properly as direction of Engineer.
After filling of sand or concrete upto the require level a plug of concrete will be provided over it as shown on the drawing.
09. WELL CAP :
Ø
A reinforced cement concrete well cap
will be provided over the top of the staining in accordance with the drawing.
Ø
Reinforcement will be assembled as per
drawing.
Ø
Bond rods of steining shall be anchored
in to the well top.
Ø Properly designed false steining will be provided as per drawings
10. CURING
:
Ø Conventional water curing will be carried out for the stipulated duration.
Ø
Hessian cloth will be used for ensuring
the proper curing work.
SAFETY MEASURES:
A) Provisions for workmen:
Ø
It is required that all persons working
at the site shall be provided with the safety equipments, protection means such
as hand gloves, safety helmets and other necessary kinds.
Ø All persons working on the site shall be trained by conducting the training course for safety to ensure that they are fully aware of the contents.
B) Provisions for Equipment, Machine:
Ø
All equipment will be ensured to
operate safely, maintained and repaired periodically.
Ø
All power equipment should be insulated
and covered to all exposed live parts.
Ø A competent person shall inspect equipment during shift duty.
C) Provisions for Job Site:
Ø
Relevant Caution boards and sufficient
lighting system shall be installed at the working area to ensure safety for
construction activities at night time.
Ø
The working area shall be free from
hazards before starting the work.
Ø
Unnecessary materials such as empty
bags and rubbish shall be removed periodically.
Ø
Proper safety measures like
barricading, guard poles painted with florescent in alternate bands, flags etc.
will be provided prior to the commencement of excavation operations.