TURFING OF SLOPES,
SHOULDERS AND MEDIAN OF
EMBANKMENT
Scope of Work :
Furnishing & Laying of live sods as to form grass on embankment slopes, verges and median as per the Technical Specifications
Materials :
The
materials proposed to be used are Local doob grass, Lemon or Lepia grass, Local
sarpat grass, Long leaved carpet grass and /or as approved by the Engineer. All
the materials used shall be devoid of any undesirable materials especially
weeds etc.
1. The area to be turfed shall have been previously
constructed to the required slope /
cross-section or else it shall be prepared to 2: 1 slope and checked by
template for continuity & exactness of slope.
2. The soil on the area to be turfed shall be
loosed upto a depth of 25 mm and made free of all undesirable foreign material.
3. Where required fertilizer /
manure shall be spread at a uniform rate by discing or any other method as
approved by the Engineer.
4. The prepared bed shall be moistened to the
loosened depth, if not already sufficiently moist.
5. The sods shall be cut in
strips of not less than 250mm x 300mm in size.
6. The sods of the specified
grass shall be placed thereon, within 24 Hrs. of cutting.
7. Every strip shall be tamped
lightly with suitable wooden or metal tempers so as to eliminate air pockets
and to press it into the underlaying soil.
8. On side slopes steeper than
2 (H) to 1 (V), the laying of sods shall be started from bottom upwards.
9. After the sods have been
laid in position, the surface shall be cleaned of loose sod, excess soil and
other foreign materials.
10. Top dressing shall be done
by scattering a thin layer of top soil and sprinkling the surface with water.
11. Proper watering and maintenance of the surface shall be done to ensure proper and uniform growth of sods for at least four weeks.
1. Warning Signs at suitable
locations shall be erected to ensure that the turfed surface is not
accidentally run over by motor vehicles.
2. Barriers shall be erected
to protect the turfed surface from stray cattle and any undesirable human
intervention.
3. Watering of the surface
shall be so done as to avoid erosion of the soil.
4. It shall be ensured that
the sodded areas are not damaged by the wheels of water trucks while
watering.
5. It shall be ensured that there occurs no harm to the sodded surface by any of the construction activities going on nearby.
CHECK LIST FOR TURFING
S.No.
|
Description |
YES |
NO |
NA |
1 |
Is
the slopes to be turfed have been completed to the lines, levels & sloped |
|
|
|
2 |
Is the topsoil has been laid |
|
|
|
3 |
Is the topsoil has been loosened
and made free from undesirable matter |
|
|
|
4 |
Is the turfing material meets the
specification and requirement |
|
|
|
5 |
Is turfing material has been cut
not earlier than 24hours |
|
|
|