Cement
concrete pavement
1.0 General
1.1 This work consists unreinforced,
dowel jointed, plain cement concrete pavement.
1.2 The Thickness of pavement slab, grade of concrete and joint details shall be as stipulated in the approved drawings.
2.0 Materials
Cement:
Ordinary port land cement of 33 grade (IS: 269), 43 grade (IS: 8112) and
53 grade (IS: 12269) may be
used but the preferences shall be to use at least the 43 grade or higher.
2.1.1
Aggregates:
2.1.2
Coarse Aggregates shall be of hard
and durable crushed stone complying with (IS: 383) but with a loss angles
abrasion Test result not more than 35 percent and water absorption shall not be
more than 2 percent. The maximum size shall not exceed 25mm. Soundness test
result in accordance with (IS: 2386) shall not be more than 12/18 percent if
sodium sulphate /magnesium sulphate is used.
2.1.3 Fine aggregate shall be of natural
sand conforming to (IS: 383). Material passing IS sieve No. 75 micron shall not
be more than 3 percent.
2.1.4
Water
Clean water free from injurious oils, salt& acid should meet requirements stipulated in IS: 456.
3.0
Proportioning of concrete
3.1 The Mix design shall be based on laboratory trial mixes as per IS: 10262 and IS:SP: 23 and strength testing shall be as per clause 903.5.2 of MOST (Ministery of Road Transport & Highways)
3.2 The cement content shall not be less than
350kg per cum of concrete and not
Exceed 425 kg per cum of concrete.
3.3 The maximum free water cement ratio shall
be 0.45
3.4 The materials and mix proportions remain
substantially unaltered during the
Day’s production.
3.5 A slump value of 30+15mm is
reasonable workability requirement for paving
Work and these tests may be carried out on alternate truckloads.
4.0 Joints
in concrete pavements
Joints may be classified as transverse and
longitudinal joints. Transverse joints are further classified as contraction,
expansion and construction joints depending upon their functional requirements.
4.1 Longitudinal
Joints:
4.1.1
These are joints between adjoining
lanes of pavement to control cracking
in longitudinal direction.
4.1.2 Tie bar of 12mm dia & 650 mm in length shall be provided at 550
mm c/c
Spacing.
4.1.3 These joints shall be saw cut as per details
in the drawings.
4.2
contraction
Joints:
4.2.1 These are straight transverse joints at specified intervals (4 to 5 mts) to Control cracking due to shrinkage and contraction as the concrete hardness.
4.1.2 Contraction joints shall consist of a mechanical sawn joint groove, 3 to 5mm wide and ¼, d/4 depth of the slab + 5mm or as stipulated in the drawings.
4.1.3 Load transfer dowels shall be of
mild steel bars of specified size (depending on thickness of pavement) and of
500 mm in length spaced at 320 mm intervals at mid –depth of the pavement slab
and should be parallel to the finished surface of the slab.
4.1.4 The dowel bar shall be supported on
cradles in pre-fabricated joint assemblies positioned prior to the construction
of the slabs or mechanically inserted with vibration into the plastic concrete.
Cradles shall not extend across the line of joint.
4.3 Expansion
Joint:
4.3.1 Relief for compression stress in hot weather is provided at
bridges and at intersections in the form of expansion joint.
4.3.2 Non-Extruding compressible filler board of entire thickness
over that polysulphide joint filling compound 20 mm thick and 20 mm less in
depth than the slab shall be provided to the full width between the side forms.
Holes shall be accurately punched to give a sliding fit on the dowel bars.
4.3.3 Joint sealing shall be of cold polysulphide type applied in accordance
with BS 5212-1990.
4.4 Surface
Texture
4.41 Texturing/Tinning shall be done with specified
designed for the purpose
Providing grooves
at an uniform spacing (c/c) of 18mm to 21 mm,depth (3mm to 4mm) and width
(3mm),parallel to the centre line of roadway extending over the entire roadway
width but within 75 mm of pavement edge & omitting within +/- 20mm of the
sawed longitudinal joints.
4.5 Equipment
(i) Batching Plant with automatic
weighing devices to proportion aggregates and bulk cement.
(ii) Pan type reversible type mixers
equipped with timing device
(iii) Centralized control cabin
(iv) Wheel loaders
(v) Tipper trucks
a) Spread b) Consolidate and c) Finish
and cure the freshly placed concrete in one complete pass of the machine. The
paver shall be equipped with electronic control.
5.0 Trial length construction
5.1 Trials shall be carried out using the same paving width and slab thickness as used in the permanent works.
5.2 The materials, plant and equipment shall be demonstrated by constructing a trial length of slab at least 60mts but not more than 300mts long.
5.3 The trial length construction shall be in two parts over a period comprising at least part of two working days minimum of 30mts each day.
5.4 Transverse joints and longitudinal joints of
each type shall be constructed and assessed in the trial length
5.5 The surface regularity shall satisfy 902.4 of MORTH (Ministery of Road Transport & Highways) and the maximum allowable difference checked with a 3mt straight – edge shall be 3mm.
5.6 Density shall be assessed from at least 3 cores drilled from each part of the trial length.
6.0 PROCEDURES
6.1 Concrete from the batching and mixing plant shall be transported by means of . Sufficient trucks/tippers without segregation and loss of slurry.
6.2 The total time taken from addition of water to the mix, until the completion of the surface finishing and texturing shall not exceed 120 minutes when concrete temperature is less than 250c and 90 minutes if it is between 250c to 300c and work may not be continued if the temperature of concrete is more than 300c.
6.3 If considered necessary the paving machines
shall be provided with covers to protect the surface of the slab under construction from direct sunlight and rain
or hot wind
6.4 The concrete shall be placed with an approved fixed formwork construction
in
Restricted areas in small lengths
may be hand-guided method.
6.5 After final regulation of the slab the surface of concrete shall be brush – textured in a direction at right angles to the longitudinal axis of the carriageway. The brush shall be not less than 450mm wide and made of 32 gauge tape wires 100 mm long spaced at 10mm centre and the brush shall have two rows of tufts 20mm apart. The texture depth shall not be greater than 1.25mm.
6.6 Immediately after surface texturing, the surface and sides of the slab be cured by application of curing compound using mechanical sprayers. After three hours the Pavement shall be covered by moist hessian kept damp for a minimum period of 14 days. No vehicular traffic shall be allowed within a period of 28 days of pavement Construction and until the joints are permanently sealed.
7.0 TESTS REQUIRED:
Quality control test as per 903.5.1 of
MORTH (Ministery of Road Transport & Highways) shall be carried out.
0 Comments
Please do not enter any spam link in the comment box.