METHODOLOGY FOR BRIDGES
General :
Concrete bridge
can be grouped according to their type into ordinarily reinforced and PSC
bridges, ordinary reinforced bridges cannot be used in long span bridges,
pre-stressed bridge are utilize to over come the above mentioned limitations of
ordinary reinforced concrete bridges.
With reference to
the Construction Methodology Concrete bridge can be classified into six
techniques:-
1.
Cast-in-situ
2.
Cantilever Carriageway
3.
Flying shuttering
4.
Launching girder
5.
Pre-cast bal cantilever
6.
Incremental Launching.
We are presently
using Cast-in-situ, before start of construction work care must be taken to
ensure that the following documents are available:
(i)
Sanction letter and technical note, if any enclosed
with the letter.
(ii)
Copy of set of plans and approved detailed working
drawings.
(iii) Standard
specification, guidelines, codes of practices etc according to which the work
must be executed as per contract.
(iv) Survey,
investigation and sub-soil test reports
Based on the study of the document,
drawings and visits to site decide the following:
(i)
Location of camp site which should include space for
batching plant, storage sheds, casting yards, sheds for equipment and
machinery, labour camp etc. Care should be taken to see that the land selected
for the above purposes is on high ground well above the highest flood level
recorded in the area with good drainage facilities, convenient approaches from
existing roads etc.
(ii)
Time required for site clearance and functioning of
camp site.
(iii) Evaluate
the existing plants and equipments to ascertain their output and plan for the
procurement of additional units, if required, for the timely completion of the
project.
(iv) Evaluate
the number of skilled and unskilled labour and the period required for bringing
them to site.
1. ALIGNMENT
After having cleared the site and
finished the camp work, the next step is to fix the alignment of the bridge on
ground. This should be done by following the layout plan with reference to the
permanent benchmarks or pillars which may have been fixed at site during the
location survey. The bridge alignment can then be marked on the ground so that
the distances and radii of curvature as laid on the ground tally with those shown
on the plan.
Once the alignment of the centre
line of the bridge has been transferred to the ground, this line should be
extended on both ends to about 50-60 meters outside from either end of the
bridge and pucca pillars should be fixed at such extended points and the
centerline precisely marked on top of these pillars. In between the reference
pillars and the end abutment, another reference pillar about 20-30 meters away
from the abutment should also be fixed.
The construction of various
components of bridge works and protective works shall conform to Ministry of
Transport Specification for Road and Bridge Works and relevant IRC Bridge
Codes/ Standards. However, some of the salient points are mentioned below:-
2. Materials
All materials to be used in the
work shall be tested to ascertain that they conform to the standards laid-out
in the prescribed specifications. The basic standards to be referred are as
follows:
1. Cement. IS 12269
2. Coarse Aggregates – IS:383 and Table no 1000-1
of MORT&H
3. Sand
– IS: 383 for cement concrete work.
4. Steel
All reinforcing bars shall be high yield strength deformed
bars ( Grade designation S415) conforming to IS 1786 ( expect for mesh
reinforcement which shall be MS bar grade designation S 240 conforming to IS :
432 part I ).
5. Water:
Normally potable water free from deleterious materials may be considered
satisfactory for mixing and curing concrete. Water to be used in concreting and
curing shall conform:
PH
value Min.6
Alkalinity Max. 10ml HCL to neutralize 200 ml water.
Acidity Max 2 ml
NaOH to neutralize 200ml water
Organic 200 mg /ltr
Inorganic 300 mg/ltr
Sulphate 500 mg/ltr
Chloride 500
mg/ltr
Suspended
matter 200mg/ltr
6. Admixtures: Admixtures shall confirm to the
requirement of IS 9103, in addition to
the conditions mentioned in cl 1012 of MORT&H shall be satisfied.
Admixtures are
used to modify the following properties
a)
Workability of fresh Concrete
b)
Pumpability
c)
High Strenth through reduction of Water content.
Minimum quantity of cement to be
used shall not be less that 210 Kg per cubic meter in plain concrete and not
less than 300 Kg per cubic metre in reinforced concrete structural members. The
minimum quantity of cement for prestressed concrete members shall neither be
less than 360 Kg per cubic metre of concrete nor shall it be more than 540 Kg
per cubic metre of concrete. This shall conform to MORT&H specification NO 1700 & Table nos 1700-2 ,1700-3 ,1700-4, for Road and Bridge Works.
3. Requirements for Design Mixes
These shall conform to MORT&H
Specification NO 1700 & TABLE 1700-1
for Road and Bridge Works.
4. Equipment
(a) Batching Plant (Make SCHWING
STETTER) (Capacity 30Cums/hr)
(b) Concrete Transportation
(a) Concrete
dumpers
(b) Power
hosts
(c) Transit
truck mixer
(d) Concrete
pump
(C) Compaction of
concrete
(a) Internal
vibrators
(b) Form
vibrators
Mixing of Concrete
Concrete shall be mixed in Batch
Mixing plant (Schwing Stetter 30cu.m/hr).Concrete mixer or Hand mixing is not
allowed.
Transportation Laying
and Compaction of concrete:
Concrete shall be transported and placed as near as
practicable to its final position, so that no contamination, segregation or
loss of its constituent materials takes place. Concrete shall not be freely
dropped into place from a height exceeding 1.5 meters.
Internal vibrators shall normally
be used for compaction of concrete. The diameter and size of the vibrators
shall be chosen, depending on the thickness of the member, maximum size of
aggregates, spacing of reinforcement etc. The vibrator shall be inserted and
withdrawn out of the concrete slowly avoiding over-vibration and segregation.
The withdrawal of the needle shall be completed by the time the cream of mortar
appears on the surface. External vibrators may be used for slender prestressed
members in addition to internal vibrators. For large horizontal areas not
exceeding 200mm in thickness, screed vibrators may be advantageously used. The
entire vibration activities must be completed before the concrete starts
setting.
Curing: All concreting shall be cured for a period of not less than
14 days from the date of placing. Curing usually consists of maintaining the
formwork in place and curing the concrete with materials such as straw,
hessian, sand, polythene sheet or curing compound or with an absorbent material
which is kept damp. Special methods of curing shall be restored to where the structural
members are of considerable depth or bulk or have an unusually high proportion
of cement content. Alternate wetting and drying shall be avoided especially in
the form of cold water applied to warm concrete surface.
Construction joints: The location of construction joints shall be
determined before the concreting starts. Any dirt or unsound concrete shall be
removed before the concreting is restarted. Dry old concrete surface against
which the fresh concrete is to be placed shall be kept moist for at least 24
hours to minimize the differences in shrinkage between the new and the old
concrete. However at the time of adding new concrete, the surfaces of the old
concrete shall be dried partially to enable the cement paste of the newly
placed concrete to bound properly with the old concrete.
OPEN FOUNDATION CONSTRUCTION
1. Sources of Material: -
The Coarse Aggregates will be
procured from our own Crusher Plant. Fine Aggregates will be procured in the
form of river sand, which is readily available in and around the project
corridor. Cement and Steel will be procured from approved manufacturer and the
manufacturer’s test certificate will be obtained. Materials shall conform to
Section 1000 of Ministry’s Specifications. Concreting shall be done as per Section
2300 of Ministry’s Specifications
2. Earth Work
Excavation for Foundations shall be carried
out in accordance with Section 300 of MORT&H.
3. Design, Erection and
Removal of Form work: -
All formwork and reinforcement
contained in it shall be cleaned and made free from standing water, dust, snow
or ice immediately before placing of concrete. No formwork is necessary for the
lean concrete layer but it may be done if directed by the Engineer. Side
formwork shall be used for foundation concrete work. All materials for formwork
will conform to IRC: 87.
Formwork shall be removed not
earlier than 24 hours after placing of concrete. The design and erection of
formwork shall be as per IRC-87 and conforming to the specifications.
4. Dewatering and Protection:
-
Open foundations shall be laid
dry. Where water is met with in excavation due to stream flow, seepage,
springs, rain or other reasons, we will be resort to providing drainage
channels, and the foundations trenches dry when so required and to protect
green concrete/masonry against damage by erosion or sudden rising of water
level. The methods to be adopted in this regard and other details thereof shall
be left our choice but subject to approval of the Engineer.
5. Preparation of Foundations:
-
The bottom of the foundations
shall be leveled both longitudinally and transversely or as directed by the
Engineer. Before footing is laid, the surface shall be slightly watered and
rammed. In the event of excavation having been made deeper than that shown on the
drawings or as otherwise ordered by the Engineer, the extra depth shall be made
up with concrete or masonry of the foundations.
6. Production, Transportation,
laying and Curing of Concrete: -
The concrete design mix will be
furnished by us for your approval before the inclusion of the same in the
actual work. The concrete will be produced by Batch Mixing Plant and will be
transported to the site of placement with the help of Transit Mixers. The
concrete will be laid in place and compacted to the form with the help of
needle vibrator.
The curing of concrete exposed surface will be done by
applying wet Hessian/Jute cloth and sprinkling of water on the vertical faces.
The horizontal faces will be cured by making water pond.
7. Person employed for execution
and supervision: -
Bridge Engineer will be employed
at site of work for control of various activities and will be assisted by site
Engineer and supervisor who will be posted at each location.
8. Tests and sampling
procedure: -
The materials will be test as per
Sec 900 of MORT&H and the procedure of relevant IS and IRC Codes
will be followed.
6. Equipment Details: -
Following equipments will be used
for the production, placing, and compaction of concrete:
(a) Batch Mixing Plant (Make
Schwing Stetter)(Capacity 30Cums/hr).
(b) Transit Mixers (TATA)
(c) Concrete Pump (Make Schwing
Stetter)(Capacity 46Cums/hr)
(d) Needle Vibrators – As per the
requirements
7. Your staff shall be apprised
before the commencement of each item of work and request for checking of every
step of work through documented Requisition of Inspection of Work.
Placing Of Reinforcement
Reinforcement steel shall conform
to the dimensions and shapes given in the approved Bar Bending Schedules.
Reinforcement bars shall be
placed accurately in position as shown on the drawings. The bars crossing one
another shall be tied together at every intersection with binding wire .the
diameter of binding wire shall not be less than 1 mm.
Necessary stays, concrete /
polymer cover blocks, metal chairs, metal hangers, supporting wires etc or
other subsidiary reinforcement shall be provided to fix the reinforcement
firmly in its correct position.
Placing and fixing of reinforcement shall be inspected and approved by
the Engineer before concrete is deposited.
Sub-structure Construction of
EXCAVATION FOR STRUCTURES
1. Scope
Excavation for structures shall consist of the removal of
the material for the construction of foundations for bridges, culverts, retaining
walls, head walls, cutoff walls, pipe culverts and other similar structures, in
accordance with the requirement of MOST and additional (as per contract)
specifications and the lines and dimensions shown on the drawings or as
indicated by the Engineer. The work shall include draining and pumping. The
removal of all logs, stumps, grubs and other deleterious matter and
obstructions, necessary for placing the foundations; trimming of excavations;
backfilling and clearing up the site and disposal of all surplus material.
1. Sources of Materials: -
The Coarse Aggregates will be
procured from our own Crusher Plant. Fine Aggregates will be procured in the
form of river sand, which is readily available in and around the project
corridor. Cement and Steel will be procured from approved manufacturer and the
manufacturer’s test certificates will be obtained. Materials shall conform to
Section 1000 of Ministry’s Specifications. Concreting shall be done as per
Section 2300 of Ministry’s Specifications.
2. Design Erection and Removal
of Formwork: -
Side form work shall be used fro
foundation concrete work. All materials for formwork will conform IRC:87.
Formwork shall be removed not earlier than 24 hours after placing of concrete.
The design and erection of formwork will be as per IRC-87 and conforming to the
specifications. We will furnish the design of formwork for your approval before
the erection of the same. It shall be ensured that the forms are removed
without disturbing the concrete.
3. Production, Transportation,
Laying and Curing of Concrete: -
The concrete design mix will be
furnished by us for your approval before the inclusion of the same in the
actual work. The concrete will be produced by Batch Mixing Plant and will be
transported to the site of placement with the help of Transit Mixers. The
concrete will be laid in place and compacted to the form with the help of
needle vibrator.
The curing of concrete exposed
surface will be done by applying wet Hessian/jute cloth and sprinkling of water
on the vertical faces. The horizontal faces will be cured by making water pond.
4. Person employed for
execution and supervision: -
Bridge Engineers will be employed
at site of work for control of various activities and will be assisted by
supervisors who will be posted at each location.
5. Tests and sampling
procedures: -
The materials will be test as per
Sec 900 of MORT&H and the procedure of relevant IS and IRC Codes
will be followed.
Equipment details: -
Following equipments will be used
for the productions, placing, and compaction of concrete.
(a) Batch Mixing Plant (Make
Schwing Stetter)(Capacity 30Cums/hr).
(b) Transit Mixers (TATA)
(c) Concrete Pump (Make Schwing
Stetter)(Capacity 46Cums/hr)
(d) Needle Vibrators – As per the
requirements
7. I C staff will be apprised
before the commencement of each item of work and request for checking of every
step of work through documented Requisition of Work
3.5 Backfilling: -
Backfilling shall be done with
approved material after concrete or masonry is fully set and carried out in
such a way as not to cause undue thrust on any part of the structure
Super structure Construction of Minor Bridges
1. Sources of Material: -
The Coarse Aggregate s will be
procured from our own Crusher Plant. Fine aggregates will be procured in the
form of river sand, which is readily available in and around the project
corridor. Cement and Steel will be procured from approved manufacturer and the
manufacturer test certificates will be obtained. Materials shall conform to Section
1000 of Ministry’s Specifications. Concreting shall be done as per Section 2300
of Ministry’s Specifications.
2. Designs, Erection and
Removal of Formwork: -
The design and drawings of complete formwork will be
produced for the approval of the Engineer, before the erection is taken up. Not
withstanding any approval of review of drawing and design by you, we shall be
entirely responsible for the adequacy and safety for formwork and staging,
The designing of the formwork
shall conform to the provisions of IRC: 87.
(a) Soffit of Slabs (with props
left under) : 3 days
(b) Props (left under slabs) : 14 days
3. Production, Transportation,
Laying and Curing of Concrete: -
The concrete design mix (if
required) will be furnished by us for your approval before inclusion of the
same in the actual work. The concrete will be produced by Batch Mixing Plant
and will be transported to the site of placement with the help of Transit
Mixers. The concrete will be laid in place and compacted to the form with the help
of needle vibrator.
The curing of concrete exposed
surface will be done by applying wet Hessian/Jute cloth and sprinkling of water
on the vertical faces. The horizontal surfaces of slab will be cured by making
water pond.
4. Personnel employed for execution
and supervision: -
Bridge Engineer will be employed
at the site of work for execution of superstructure work. Pour cards will be
maintained at site for concrete pouring record and supervision by our staff.
5. Tests and sampling
procedures: -
The materials will be test as per
Sec 900 of MORT&H and the procedure of relevant IS and IRC Codes
will be followed.
6. Equipment details: -
Following equipments will be used
for the productions, placing, and compaction of concrete.
(a) Batch Mixing Plant (Make
Schwing Stetter)(Capacity 30Cums/hr).
(b) Transit Mixers (TATA)
(c) Concrete Pump (Make Schwing
Stetter)(Capacity 46Cums/hr)
(d) Needle Vibrators – As per the
requirements
7. Our staff will be apprised
before the commencement of each item of work and request for checking of every
step of work through documented Requisition of Inspection of Works, will be
forwarded.
Bearings: Installation procedure for bearings shall conform to the
provisions contained under section 2000 of the “Specifications for Road and
Bridge Works”. and IRC : 83-part II -1987 for Electrometric bearings However
some of the important points are as follows:-
(i)
Prepare wooden casing with inner dimensions as per the
size of pedestal. Place the reinforcement and wooden template along with
foundation bolts inside the wooden casing.
(ii)
Pour concrete inside wooden casing as per
specifications and allow it to set for a day.
(iii) Next
day take levels of all pedestals.
(iv) Put
thick concrete paste, if required to make height of all pedestals equal and allow
it to set.
(v)
Pour liquid slurry over bearing area, place the bearing
and tighten foundation nuts. This removes unevenness in pedestal-top and gives
uniform support for bearing.
(vi) Cross
check levels for the bearing top surface after placing all the bearings.
(vii)Fix anchor
bolts to the top plates of bearings.
(viii) Place
the reinforcement for superstructure onto the bearings and cover bearing with
cotton-waste from sides to protect from ingress of dust.
(ix)
Pour concrete for superstructure and allow it to cure.
(x)
Remove temporary fixtures provided for bearings. The
bearings are then ready for use.
(xi)
All bearings of the lot shall be visually inspected
for any defects in surface finish, shape or any other discernable superficial
defects.
(xii)
Each elastomeric bearing shall be clearly labeled
or marked, The bearing shall be warped in a cover. They shall be packed in
timber crates with suitable arrangement to prevent their movement and to
protect corners and edges.
(xiii)
Care shall be taken to avoid mechanical damage,
contamination with oil, grease, dirt, undue exposure to sunlight and weather to
the bearings during transport storage and handling prior to and during
installation.
(xiv)
Bearings must be placed between the two horizontal
surfaces (maximum tolerance 0.2 per cent perpendicular
Expansion Joints:
Studies approved
drawings and ensure that adequate anchorage arrangements are available for
anchoring of expansion joints to the body of the main bridge deck. The
expansion joint shall be placed in position in accordance with the approved
drawings and specifications Section 2100 of “Specifications for Road and Bridge
Works” maintaining specified cross slope
of the deck, expansion gap, placement of seal etc.
Concrete Crash Barrier
The location of
crash barrier shall be strictly adhered to as shown on the drawing. Concrete
crash barriers shall present smooth, uniform appearance in their final
position, conforming to the horizontal and vertical lines shown on the plans
and shall be free of lumps, sags or other irregularities. The top and exposed
faces of the barriers shall conform to the specified tolerances, as defined in
clause 809.4, when tested with 3 m straight edge laid on the surface.
All materials
shall conform to section 1000-Materials for structures as applicable, and
relevant Clauses in Section1600 shall govern the steel reinforcement.
Formwork, Centering etc:
The designs and
erection of formwork and centering shall conform to IRC:87 ‘Guidelines for the
design and erection of False work for Road Bridges” and Section 1500 of ‘ Specifications for Road and Bridge Works’
and got approved by the Engineer-in-Charge before start of work.
Design Standards and
Specifications:
Bridges
1. Design Criteria
The design is in accordance with the
following codes.
a) Foundation (open)
1) IRC: 6-1966
2) IRC : 21-1987
3) IRC :
78-1983
b) Substructure
1) IRC : 6-1966
2) IRC : 21-1987
3) IRC :
78-1983
c) Superstructure
1)
IRC : 21-1987
d) Bearings
1) IRC :
83-part II -1987 for Electrometric bearings
e) Expansion
Joints -
In accordance with MORTH letter No. RW/NH-34059/1/96- S&R dated
30.11.2002.
f) Protection Works
1)
IRC : 89-1997
The following loads have been considered in design :
1) One lane of IRC class 70R or two lanes of IRC
class A or one lane of IRC
Class AA
tracked vehicle on carriageway, whichever governs.
2) Seismic Analysis - The proposed bridges fall in seismic zone IV
as per the
Classifications given in IRC : 6-1966 and are designed for seismic
coefficient
Of 0.05 ,
importance factor of 1.5 and Value of B = 1.2.
3) Effect of Wind - The
proposed Structures have been designed for wind effects as per clause 212 of
IRC : 6-1966
4) Safe Bearing Capacity of soils - As per site condition at foundation level.
5) Wearing Coat --- Asphaltic concrete wearing
coat of 50mm thick provided in
Two
layers of 25mm thick each overlaying 6mm thick mastic asphalt.
g) Reinforcement
(As stated above)
h) Water (As stated above)
i) Bearings
Elastometric bearings shall conform to IRC : 83-1987(Part II)
Workmanship/Detailing
1. Min.clear cover to all
reinforcement including stirrup’s shall be 50mm unless shown otherwise in the
drawings.
2. For
ensuring proper cover of concrete to reinforcement specially made polymer cover
blocks shall only be used.
3.
Construction Joints
a)
Construction Joints shall be provided only at location directed/approved by
Engineer in charge shown on the drawing. Concreting operation shall be carried
out continuously up to the construction Joints.
b) The concrete surface at the joint shall be
brushed with a stiff brush after casting while the concrete is still fresh and
it has only slightly hardened.
c) Before new concrete is poured, the surface of
old concrete shall be prepared as under.
i) For hardened concrete, the surface shall be
thoroughly cleaned to remove debris and laitance and made rough so that ¼ of
the size of aggregate is exposed but without dislodging the aggregate or
structurally damaging the concrete.
ii) For partially hardened concrete, the surface
shall be treated by wire brush followed by an air jet. The old surface shall be
soaked with water , without leaving puddles, immediately before staring
concreting to prevent absorption of water from new concrete.
d) Welding to reinforcement bars shall not be permitted.
e) Laps in reinforcement;
a.
Min .lap length of reinforcement shall be kept as.
i.
83d for superstructure
ii.
55d for substructure and foundation (where d is the
diameter of reinforcement bar.)
b.
Not more than 50% of reinforcement shall be lapped at
any one location.
f) Bending
of reinforcement bars shall be as per IS: 2502.
g) Supporting
chairs shall be provided at suitable intervals as per IS: 2502.
h) Concrete
shall be produced in a mechanical mixer of capacity of not less than 200 liters
having integral weighed batching facility and automatic water measuring and
dispensing device. Proper compaction of concrete shall be ensured by use of
form and / or needle vibrators. Use of full width screed vibrators for
compaction of concrete in deck slab shall ensured. Shuttering plates shall
suitably be stiffened to enable the compaction by form vibrators if used sharp
edges of concrete shall be chamfered. The location of jacks for lifting up the
superstructure to replace bearings etc is indicated in drawing. This shall be
distinctly etched on one cross girders and pier/abutment caps.
.
0 Comments
Please do not enter any spam link in the comment box.