Ad Code

Responsive Advertisement

METHODOLOGY FOR ROAD KERB

                               METHODOLOGY FOR ROAD KERB


This article covers constructing cement concrete kerbs and kerbs with channel with the lines, levels and dimensions as per approved drawings.

The work involves construction of in Situ- Cement Concrete Kerb & Kerb with channel along medians, junctions, edges, service Road, separators etc. to the line, level and dimensions as shown in the contract drawings.

    Materials

Kerbs and kerb with channel will be provided in cement concrete of grade M20 in accordance with Section 1700 of M.O.S.T. Specifications. The cement concrete mix shall be produced to the required slump to achieve the specified scope and smooth finish. . 

ROAD KERB

 Construction Methodology

This work will be done as per technical specification clause 408.

The total quantity of kerbs and kerb channels as per the Bill of Quantities in Running meter.

The above quantity is for the entire stretch and planned for execution as per the construction program. 

Cement Concrete will be transported through transit mixer of 6m³ capacity.

  SUMMARY OF PROPOSED EQUIPMENT:

a.       Kerb machine with extruder.

b.      b. Concrete Truck/Transit mixer.

c.       c. Joint cutter.

                                                   

         Manpower

Skilled Manpower to drive that machinery is as follows (With each crew):

           Engineer                           -           1 No.    .   

           Surveyor                           -           1 No.   

           Mason                               -           1 No.

           Transit Mixer Opt             -           2 Nos.

           Kerb Machine Opt           -           1 Nos

           Helper                                -           1 nos.

                 W/Tanker Driver               -           1 Nos.

                 Labour                               -           4 Nos.

 

   Construction Operation

The surface level of WMM on which the road kerb is to be laid is to be made up with the leveling course in order to lay the kerb.

The level will be maintained and checked in reference to the finishing level of the roadwork with auto Level through sensor system of machine. The road kerb machine will travel on the WMM surface.

The mixed concrete M-20 with very low slump (at the time of pouring in the hopper of machine) carried in transit mixers from the batching plant and will be poured into the hopper of the road kerb machine. The slump at the batching plant to be kept between 25 to 30mm and slump will be increase or decrease with the help of increasing or decreasing the dose of super plasticizer as per the requirement. The most important point is that the slump should be zero at the point of pouring concrete in to the hopper of road kerb machine.

There shall be no honeycombing or irregularity in the surface area. If during casting kerb, it is found necessary to repair / touch up, a mason with helper will move along the machine and repair.

After the concrete is finally set, the kerb will be cut at a interval of 5m or as per requirement of ground conditions with concrete cutting machine.

The portion near to culverts and bridges where the kerb cannot be laid with machine, the same will be laid with precast units as per MOST specification.

Freshly cast kerb will be covered with hessian cloth / gunny bags and kept moist with water for 7 days as the concrete will achieve a good strength, since slump of the concrete at the time of kerb casting is almost zero.

Alternatively, approved curing compound may be applied on the kerb immediately after casting if decided by the Engineer.


 CHECK  LIST  FOR  KERB  LAYING 

Location          :                                                                       Date                :

 

Layer               :                                                                       Inspection No.           :

S.No.

 

Description

YES

NO

NA

1

Previous layer is approved

 

 

 

2

Mix and its materials are approved

 

 

 

3

Concrete conveying arrangement (including transit mixers) available in working conditions and of sufficient capacity

 

 

 

4

Alignment

 

 

 

5

Level

 

 

 

6

Dimension

 

 

 

7

Class of finish

 

 

 

8

Curing arrangements

 

 

 

9

Saw cut provided for expansion joints

 

 

 



Post a Comment

0 Comments