METHODOLOGY FOR DRY LEAN CONCRETE
Providing and laying dry lean concrete
complete as per drawings & technical specifications Clause No. 601.
1.
MATERIALS
Sources
of materials shall be as under : -
a) Coarse Aggregates : Quarry,
b) Fine Aggregates : Quarry,
(Stone Dust )
River
Sand,
c) Cement : 43 Grade OPC
d) Water : Bore well
QUALITY
ASSURANCE: Test
certificates from manufacturer shall be presented for each lot of cement or
cement testing shall be carried out in our site laboratory and result will be
submitted. Joint test shall be carried out for the approval obtained from the
Engineer’s Representative for every 200cum of material. Water shall be tested
as per requirement of IS: 456 and approval obtained in advance.
Cement
shall be procured in polyethylene Bags and loaded manually in to hopper of
cement pump. From hopper of pump it will be pumped to the Silo of the Batching
Plant.
Combined
grading of aggregates (Coarse & Fine) will be carried out at laboratory
attached with the plant, at least once daily and adjustments in Mix proportions
will be made for aggregates components, accordingly.
All
approved aggregate shall be stacked separately at plant site in stack 5.00
Meter clear Distance apart and shall be identified by placards marked
‘APPROVED’ placed on top of the heap.
2. MIX - DESIGN
The mix shall be proportioned with a
maximum aggregate cement ratio 15:1. The right amount of water will be decided
so as to ensure full compaction under rolling and will be assessed at the time
of rolling the trial length. As the too much water will cause the lean concrete
to be heaving up before the wheels and picked up on the wheels of the roller
and too little will lead to inadequate compaction, a low in-situ strength and
open textured surface, the optimum moisture content and degree of compaction shall be determined
during the trial length. These
parameters can be decided during the trial length and be approved by the
Engineer.
The minimum cement content in
the lean concrete shall not be less then 150 kg/cum of concrete. If the minimum
cement content is not sufficient to produce concrete of the specified strength,
it will be increased as necessary. The average compressive strength of each
consecutive group of 5 cubes made in accordance with clause 903.5.1.1 will not
be less than 10 Mpa at 7 days. The design mix
meeting these requirements will
be got approved from the Engineer and demonstrated in the trial length
construction.
Construction Process
a.
Preparation
of Surface: Loose patches on the drainage layer shall be
watered and compacted to achieve a firm surface. Prior approval of length of
every days’ paving shall be obtained in advance. As for as possible the construction traffic
shall be avoided on the prepared surface. A day before placing of the lean
concrete, the sub surface shall be given a fine spray of water and rolled with
one or two passes of a smooth wheeled roller after a lapse of 2-3 hours in
order to stabilize the loose surface.
b.
Concrete
Production: Concrete shall be produced in the Batching
Plant, which is capable of proportioning the material, by weight, with each
type of material being weighed separately. The batching and mixing shall be
carried out in a forced action central batching and mixing plant, which has
automatic control. The controls are fully computerized so as to ensure accurate
proportioning and mixing. The accuracy of weighing scales of the batching plant
will be within +/- 2 percent in the case of the aggregates and +/- 1 percent in
the case of cement and water. Additives will be introduced into the mixture in
diluted form. Loaders will be used to load aggregates from stacks of approved
material into bins. Batch plant bins will have a storage capacity of 35 cum
each. Water will be obtained from the bore wells at the plant site. Water will
be stored in the water tank of 120 kl capacity. Mixing time shall be
established to the satisfaction of the Engineer’s Representative. Concrete will
not be produced when ambient temperature fall below 5 deg centigrade of exceeds
35 deg cent. Following measures to control temperature within 30 deg cent will
be adopted.
i)
Mechanically
water will be sprinkled to cool the aggregate.
ii)
Cover
will be provided for aggregate to be used in next 24 hours.
iii)
Chilled
water will be used for preparation of concrete. For this purpose water chilling
plant of capacity 15000 lt/hour capacity and storage of 50000 lt will be used.
Transportation: Plant mix lean
concrete shall be discharged immediately from the mixer, transported directly
to the point where it is to be laid and protected from the weather by covering
the tippers/dumpers. The concrete will be transported by tippers/ dumpers of 6
cum capacity and sufficient in number. The number of the tippers be adequate in
number so as to feed the Paver to work at a uniform speed and in an uninterrupted
manner.
PLACING:
a)
the
work will be carried out with Paver of laying capacity 8.5 meter of main
carriageway in one pass. The balance portion on both the sides of the
carriageway will be laid manually.
b)
Surveyor
will fix the alignment for every day’s work, one day in advance, and get it
approved from Engineer’s Representative.
c)
Prior
to start of paving, string line will be set, approx. 200mm above DLC top levels
on each side, on longitudinal profile, on stakes placed 10 met apart.
d)
Air
and concrete temperature shall be measured and recorded in the concrete
docket, at the plant site as well as
laying site. No concrete will be done when the concrete temperature cannot be
maintained below 30 deg cent & and when ambient temperature is more then 35
deg cent. Plant operation will be stopped based on feed back from laying site.
e)
Tracibility
of concrete received from the batching plant will be maintained by recording
data as shown on Tracibility form.
Compaction:
a)
Rolling
shall be done by double drum vibratory roller of 80 KN static weight and shall
commence immediately after laying by Paver. First pass of the roller shall be
given in static mode and there after roller shall be operated in the vibratory
mode. Sufficient number of passes would be given till the density of compacted
layer reaches more than 97% of Dry density achieved in Trial length
construction. Areas inaccessible for the roller will be compacted by plate
vibrators. Static roller will be used as stand by in the event of breakdown of
vibratory roller but further work will not be carried out till the vibratory
roller is available in working condition at site.
b)
Honey-combed
surfaces shall be corrected by scarifying and repairing with concrete prepared
with aggregate of 10 mm size before start of rolling operations.
c)
Surface
regularity during the course of laying will be checked with a 3 meter straight
edge. High points of the surface will be corrected by scarifying & rerolling and the low areas shall be
corrected by filling with fresh materials and rolling.
The spreading,
compacting and finishing of the lean concrete shall be carried out as rapidly
as possible and the operation shall be so arranged as to ensure that the time
between the mixing of the first batch of concrete in any transverse section of
the layer and the final finishing of the same shall not exceed 90 minutes when
the concrete temperature is above 25 and below 30 degrees Celsius and 120
minutes if less then 25 degree Celsius. However, these parameters will be
decided in the trial length.
CURING: As soon as the lean concrete surface
is compacted curing shall commence. Hessian shall be used and will be kept
moist for 7 days by regular sprinkling of water from flexible pipe attached
with a water tanker. Water tankers will be deployed round the clock for
providing water for curing. Water will be available from the bore wells along
the length of the road.
3. TRIAL
PAVE
a)
Trial
paving will be conducted at outside the road alignment and at our campsite at
Km 167 or near Km 180.
b)
Length
of laboratory Pave shall be kept as 60-70 meter.
c)
Target
level for the Trial shall be fixed prior to paving.
d)
Suitability
of moisture content of Mix shall be examined during the trial length
construction to ensure that maximum density and compressive strength related to
corresponding water content are achieved.
e)
Density
of compacted materials of trial length will be determined as specified and
taken as reference density. Approval of trial length shall be obtained from the
Engineer.
f)
3-meter
wide portion of hardened concrete of trial length shall be cut and reversed for
inspection of bottom surface. The entire process of mix design & trial
length shall be repeated if segregation of mix is observed.
g)
Achieve
levels will be compared with the target levels.
h)
Approval
of Engineer’s representative will be obtained before proceeding with the main
work.
TESTING: Testing will be carried out as per
table enclosed ( Encl –III). Level conformance of finished DLC will be ensured
by taking levels at specified grids and compared with the target levels.
Concrete testing record will be maintained as per format enclosed ( Encl- IV).
Tolerances: The tolerances for surface
regularity, level, thickness, density and strength shall conform to the
requirements given in clause 903.5. Control of quality of material and work
shall conform to the specification as laid down in Section 900 of MOST
Specifications.
TRAFFIC: No heavy commercial vehicles like
trucks and buses shall be permitted on the lean concrete sub-base after its
construction. Light vehicles shall be allowed after 7 days of its construction.
MACHINARY AND MANPOWER: Machinery and manpower will be
deployed as detailed in encl-V.
i)
Is
representative will be obtained before proceeding with the main work.
4) Environmental Safety
I.
Water
will be obtained from the bore wells situated at our Camp Sites so that it will
not affect near by localities.
II.
The
Batching Plants are situated at our Camp Sites at Km167.00 and water sprinklers
will be installed to minimize Dust & Cement in the localities.
III.
Fuel
Storage and Refueling at Site are in the Camp Sites and Strict Supervision will
be maintained to stop Spillage or leakage to any near by water bodies.
IV.
Our
Mechanical Staff will maintain Batching plant & other related equipments
regularly to reduce Noise & Atmospheric Pollution.
V.
The
constructions Vehicles, Machineries and Equipments will move in our designated
area so it prevents compaction of any type of vegetation and plants.
VI.
All
workers will be suitably provided with safety guards at the site.
VII.
Safety
Signals & Sign boards will be provided at every 200 m at the Construction
Site.
0 Comments
Please do not enter any spam link in the comment box.